RCC Road Construction is a technical aspect and required standard benchmarking system provide by,IRC, M.O.R.T.H And other agencies involve in to Monitor the quality of Work, There are Several Consultant who are involve. During the Construction or PQC Process it happens some time they are unable to add required Tie Bar they Forgot at various places at this time the Quality of work does not meet the standard.
Solution
We SB International provide the Solution for these problem by our technical team we provide Rebaring service with HILTI chemical and Testing Carried out by HILTI
1
2
3
4
5
Chemical
Process
Test Required
Required Aspects Values of Pull out Test
Result
HILTI
Drilling, Chemical Filling, and Inserting Rebar
Pull Test for Rebar
2.4 Kn/MM2 or 2.4 Megapascal
Test Passed in Presence of Consultant and Principle Company